Medical Center Company solar generation project facts:

September, 2014

  • MAXIMUM RATED OUTPUT CAPACITY: 1 Megawatt (MW)

  • PANELS: Total of 4,004; Kyocera (50%) and Isofoton (50%)

  • EQUIPMENT: (4) 250-kW Eaton Power Xpert Solar Inverters, (28) Eaton String Combiner Boxes

  • CONSTRUCTION STARTED: December 2013

  • INSTALLED COST: $2.70 per Watt

  • UTILITY DISTRIBUTION SYSTEM: Cleveland Public Power

The Medical Center Company (MCCo) - the not-for-profit corporation that powers many of University Circle's healthcare, educational, cultural and religious institutions - has partnered with Evergreen Energy Solutions (E2S) in the construction of this 1 Magawatt solar generation project. MCCo is also partnering with Case Western Reserve University's Solar Durability and Lifetime Extention (SDLE) Center to provide valuable research data from this project.

The cleanup of this 5 1/2 acre brownfield site was made possible with a Clean Ohio Revitalization Fund grant under the authority of Cuyahoga County and the Ohio EPA Voluntary Action Program.